Computer Network Construction Agreement
The Information Technology Department is in the process of establishing procedures for early coordination with all departments within the university regarding the completion of new construction and remodeling projects for institutional buildings. This is to ensure that internet connectivity can be promptly established upon project completion. Therefore, we kindly request that each department involved in the network construction process adhere to the following guidelines from the initial stages of the project.
Target
- Network (Communication) Construction due to New Construction, Expansion, Remodeling, and Change in Use
(*Note: Additional adjustments to wired LAN within office spaces of existing buildings, as well as LAN cable installation, are to be independently managed by individual departments)
Coordination Procedure
- Entire Procedure
Executing Organization | Context |
---|---|
1. Institution within the University | Pre-Coordination Application for Network Construction and Connection |
2. Information System&Technology | Review and Confirmation of Network Configuration (Draft) and Allocation of Necessary Resources |
3. Institution within the University | Build according to the provided guidelines |
4. Institution within the University | Requesting Campus Network Connection (e.g., IP Request) |
5. Information System&Technology | Network Connection and Speed Inspection |
6. Institution within the University | Transition of Network Equipment Management |
- Pre-consultation application for computer network construction and connection:
Apply via Seoul National University Portal (my.snu.ac.kr) → [SNUin Support] → [IT Services (ITSM)] → [Service Request] → [Network Services] → [Campus Computer Network Collaboration Services] → [Construction Collaboration and Computer Equipment Management Transition] (Manual Download) - Network Connection and Speed Check: Inspection of cable laying and labeling is possible only when the attached guide is followed (Installation Guide)
- Network Equipment Management Transition: After the inspection is complete, if a management transition is necessary, the institution that carried out the construction through integrated administration can proceed with the transfer of computer equipment asset management to the Information Headquarters Information Support Department (Management Transition Non-Implementation Guide, Management Transition Implementation Guide, Management Transition Form)
- Others: Application for using switch ports in equipment rooms, additional use of room LAN ports.
Computer Equipment Introduction Standards
Category | Content |
---|---|
Wired | Computer Network Construction and Pre-consultation Application – 24포트 : Cisco C9200-24T-4G , Arista CCS-720DT-24S , HPE ARUBA 2930F 24G – 48포트 : Cisco C9200-48T-4G , Arista CCS-720DT-48S , HPE ARUBA 2930F 48G |
Wireless | – 802.11ax (antenna internal type) Aruba AP-515 or higher |
PoE Switch | – Supports 802.11at PoE+, total support of 1,440W or more (based on 24 ports, 60W per port) – When connecting less than 5 APs in the same equipment room, install one injector per AP (supports 802.11at PoE+) – 24포트 : Cisco C9200-24P-4G , Arista CCS-720DP-24S , HPE ARUBA 2930M 24G PoE+ |
※ The equipment in the table represents the minimum specifications, and it is recommended to adopt the latest equipment available at the time of procurement